TM 551510-220-10
g.
Rotate TEST SEQUENCE switch clockwise to next
position, DISP COMPL.
19. Press pilot CHAFF DISP switch once. Press
copilot CHAFF DISP switch once. On DCP,
for each depressing, the CHAFF counter
should count down by an increment of one.
20. On DCP, set MAN-PGRM switch to PGRM
position.
21. Press any one of CHAFF DISP switches in
aircraft. In DCP, the number shown on
CHAFF counter should decrease in
accordance with the program set on the EM.
22. Repeatedly press other CHAFF DISPENSE
switch until CHAFF counter on DCP reads
00.
23. On test set, observe DISPENSE
COMPLETE lamp (green) is illuminated and
then perform the following operations:
a.
Rotate TEST SEQUENCE switch counter-clockwise
to SYS NOT RESET position. SYS NOT RESET
lamp (amber) will illuminate.
b.
Press and release MANUAL SYSTEM RESET
switch. SYS NOT RESET lamp (amber) will
extinguish.
NOTE
When the MANUAL SYSTEM RESET
switch is pressed and released, and 28 volts
DC power has been applied, the sequencer
switch inside the dispenser assembly resets,
making an audible sound as it rotates. If
the sequencer switch has been previously
reset or if the switch is in position 12 or 24,
there will be no such sound.
c.
Rotate TEST SEQUENCE switch counter-clockwise
to STRAY VOLT position. STRAY VOLTAGE
lamp (red) should not illuminate.
d.
Rotate TEST SEQUENCE switch counter-clockwise
to START/HOME position.
NOTE
When the TEST SEQUENCE switch is
turned
to
the
OFF
position,
the
DISPENSER
COMPLETE
lamp
will
extinguish, the STRAY VOLTAGE lamp
will illuminate and then will extinguish
when the OFF position is reached.
24. Install safety pins.
25. Disconnect test set power cable.
26. Remove M-91 test set from dispenser
assembly and restore in carrying case along
with the power cable and hexagonal wrench.
27. On DCP, set ARM-SAFE switch to SAFE
position.
28. On DCP, reset CHAFF counter to 30.
29. Disconnect aircraft power by pulling the 5
ampere M130 POWER circuit breaker
located on the mission control panel (fig. 4-
1).
30. Proceed immediately to ammunition loading
procedures.
4-5.
AMMUNITION.
a.
Ammunition Loading Procedure.
WARNING
Only one shipping container is to be
opened at a time. If a shipping container
has been opened and only partially
emptied, the remaining contents will be
secured
in
the
container
with
an
appropriate type of packaging material or
filler to adequately prevent jostling. All
munitions in storage must be in their
original shipping containers.
1.
Place payload module assembly on work
bench in approved safe area so that the
retaining plate is facing up.
2.
Remove retaining plate by unscrewing two
retaining bolts.
3.
Insert one flare (or chaff) at a time into each
chamber of payload module.
4.
Remove plastic dust cap from each chaff or
flare.
4-8