TM 55-1510-219-10
NOTE
Replace any lamp that does not
illuminate when pressed. If none
of the indicating lamps illuminate,
return test set to AVUM.
b.
Rotate TEST SEQUENCE
switch
clockwise
to
the
next
position, TS RESET. No visual
indication will occur.
c.
Rotate TEST SEQUENCE
switch clockwise to SV SELF TEST
position. STRAY VOLTAGE lamp
(red) will illuminate.
d.
Rotate TEST SEQUENCE
switch clockwise to next position,
TS
RESET.
STRAY
VOLTAGE
lamp (red) will extinguish.
e.
Rotate TEST SEQUENCE
switch clockwise to next position,
STRAY VOLT. STRAY VOLTAGE
lamp (red) should not illuminate.
f.
Rotate TEST SEQUENCE
switch clockwise to next position,
SYS NOT RESET. SYS NOT
RESET lamp (amber) should not
illuminate. If lamp illuminates,
press
and
release
MANUAL
SYSTEM RESET switch and SYS
NOT RESET lamp should then
extinguish.
NOTE
When
the
MANUAL
SYSTEM
RESET switch is pressed and
released, and 28 volts DC power
has been applied, the sequencer
switch
inside
the
dispenser
assembly
resets,
making
an
audible sound as it rotates. If the
sequencer
switch
has
been
previously reset or if the switch is
in position 12 or 24, there will be
no such sound.
g.
Rotate TEST SEQUENCE switch
clockwise to next position, DISP
COMP.
12.
Press FLARE DISP switch once. For each
depressing, the FLARE counter on DCP should
count down in groups of three.
13.
On DCP, raise RIPPLE FIRE switch guard and
set toggle switch to up position until FLARE
counter counts down to 00. Return switch guard
to down position. On DCP, reset FLARE
counter back to 30. DISPENSER COMPLETE
lamp (green) on test set will illuminate.
14.
Perform the following operations on the M-91
test set:
a.
Rotate TEST SEQUENCE
switch counter-clockwise to SYS
NOT RESET position. SYS NOT
RESET
lamp
(amber)
will
illuminate.
DISPENSER
COMPLETE
lamp
(green)
will
remain illuminated.
b.
Press
and
release
MANUAL
SYSTEM RESET switch. SYS NOT
RESET
lamp
(amber)
will
extinguish.
NOTE
When
the
MANUAL
SYSTEM
RESET switch is pressed and
released, and 28 volts DC power
has been applied, the sequencer
switch
inside
the
dispenser
assembly
resets,
making
an
audible sound as it rotates. If the
sequencer
switch
has
been
previously reset or if the switch is
in position 12 or 24, there will be
no such sound.
c.
Rotate TEST SEQUENCE
switch counterclockwise to STRAY
VOLT position. STRAY VOLTAGE
lamp (red) should not illuminate.
d.
Rotate TEST SEQUENCE
switch
counterclockwise
to
START/HOME position.
NOTE
When
the
TEST
SEQUENCE
switch
is
turned
to
the
START/HOME
position,
the
DISPENSER COMPLETE lamp will
extinguish, the STRAY VOLTAGE
lamp will illuminate and then will
extinguish when passing through
the TS RESET position.
15.
On CHAFF dispenser assembly, assure that C-F
selector switch is in C (chaff) position.
16.
Remove M-91 test set from first dispenser
assembly.
17.
Connect M-91 test set to breech assembly of
second dispenser assembly. Secure both
mounting studs uniformly hand tight using ball
hexagonal key screwdriver provided in test set
carrying case.
4-7